This diagram shows the amount of construction that had to go into the massive project. Before anything on the dam could be done, first diversion tunnels had to be dug to allow the river to flow around the site. The Outer tunnel on each side would later become part of the overflow path, while the inner tunnel on each side would become part of the path that takes water to the power generating station. Once the tunnels were built, large cofferdams had to be built above and below the site to prevent the river from entering, then the site had to be dried out and dug down to the bedrock. Then besides the dam, there needed to be built the power station, intake towers, spillways, and all the associated pipeways. In all, more concrete would be used on the project than all other dams built by the Bureau of Rec;amation combined.
Tunnels for the dam were dug using giant drill carriages, called Jumbos. These were trucks with massive platforms built onto them where 24 to 30 workers could drill at once. The diversion tunnels alone totalled 15,909 feet of 56 foot wide tunneling, and with the jumbo, crews averaged 16 feet every four hours. Three massive air compressor plants were constructed to operate the air operated drills in the tunnels, and a massive railroad network was created to remove the "muck", or drilled out rock. The tunnels were also coated with a three foot ring of concrete to minimize damage. This concrete, later to be used in the dam itself, was made of aggregates gathered from local side canyons, and organized by automated by machines, sorting the rocks by size. The various sizes were sent to the mixing plants where a specifically controlled process combined the exact amount of each size, with sand and water.
Following the completion of the diversion tunnels, the cofferdams needed to be completed to free the dam site of water. These were made of rock landfill from the diversion tunnels, covered with concrete under the same strict control as the tunnels and dam itself. The upper dam alone was 98 feet high, 480 feet long, and 750 feet thick. Finally, after the site was drained and silt removed, construction of the dam itself could begin. The most difficult challenge at this point was cooling the concrete. As concrete dries, it heats up around forty degrees due to the chemical reaction, and the subsequent cooling can cause large cracks to develop. This was counteracted here in two ways. The dam was built as a series of columns whose construction was staggered, offering more surface area to allow cooling. More improtantly, a series of small pipes were run throughout the concrete as it was poured, and these pipes were connected to an ammonia refrigeration plant, designed to remove excess heat and minimize the shrinkage. The concrete was poured using eight-cubic yard buckets carried by massive aerial tramways, as seen above. A crew of workers in rubber boots smooth the concrete in each block, as well as work it around pipes and instrumenst placed to measure temperature and pressure. The penstock headers, used to carry water to the power plant, were made of steel piping placed in tunnels in the rock. The manufacture of these giant pipes was such an undertaking that it was contracted to the Babcock and Wilcox Company of Barberton, Ohio for $11,000,000. They produced 14,500 feet of piping in diameters of up to 30 feet. The sections of piping, weighing around 170 tons each, required the construction of a special trailer with individually steerable wheels to transport them to the site. The hydro-electric power plant dwarfs in comparison to the massive dam, but it is actually 19 stories high with an area of four acres. When it was completed, it supplied all the power to the 8,500,000 people then living around the Colorado River Basin.
Inside one of the power plant "wings". The total power producing capacity of the plant is 1,860 Mega watts, or put another way, each cubic foot of water through the turbines produces 746 watts. Each wing also has a smaller turbine used to power local loads.
One of the controling stations for the power plant.
An Indian symbol for water or power
So, when all was said and done, the dam was completed in 1935, and the first power generated in 1936. Total cost was $49,000,000 and took 4.36 million cubic yards of concrete. 112 deaths were attributed to the construction of the dam. It has around 9 million visitors each year, and the reservoir it created, Lake Mead, is the fifth busiest US National Park unit. The lake is 157,900 acres, reaching as far as 110 miles from the dam. It was named for Elwood Mead, the director of the Bureau of Reclamation at the time the dam was built.
Some of the tools used in planning and constructing the dam.
One of the towers taking power from the power plant.
Monument to the construction of the dam
For your comic relief, his is the mens restroom, on the dam.
The giant intake towers, where the water flows into the pipes to the power plant.
Looking down the backside of the dam at the waters of Lake Mead.
Looking back at one of the concrete spillways, used only twice, in 1983 and 1999, when record precipitation caused the reservoir to reach the level of the spillway. The change in the rock color from white to red shows the highest level of the water.
The US 93 bridge being constructed in front of the dam. The road curently goes across the dam, but is being moved to the bridge due to the road's tight mountain turns and security concerns for the dam itself. The bridge is projected to be comleted in 2010.
Monument to the construction of the dam
For your comic relief, his is the mens restroom, on the dam.
The giant intake towers, where the water flows into the pipes to the power plant.
Looking down the backside of the dam at the waters of Lake Mead.
Looking back at one of the concrete spillways, used only twice, in 1983 and 1999, when record precipitation caused the reservoir to reach the level of the spillway. The change in the rock color from white to red shows the highest level of the water.
The US 93 bridge being constructed in front of the dam. The road curently goes across the dam, but is being moved to the bridge due to the road's tight mountain turns and security concerns for the dam itself. The bridge is projected to be comleted in 2010.
No comments:
Post a Comment